Five delivery schemes to win Middle East orders

Project location:Middle East

Product:Duplex stainless steel pipe and fittings

Specifications:Pipe- DN400*STD*18M length

Standard and material:UNS31803

Usage:Central Sewage Treatment Plant

Inquiry time:2021.02

Order time:2021.10

Shipping time:2022.01

Arrival time:2022.03

In the early stage of customer inquiry, after communication and discussion, the difficulty is the project start time very urgent, the customer expects to receive the products as soon as possible to start construction. In order to deliver as fast as we can, we successively submitted five versions of the production plan to the customer, also attached the production plan in detail. The considerate service made the customer choose Xinyue without hesitation.

Xinyue also did not disappoint customer, constantly informed customers of the production progress, and regularly took photos of the progress in daily report. During the same period, various preparations for shipment are also being actively handled. Under the coordination and cooperation of multiple departments, the shipment sailed smoothly before the China New Year as scheduled, which solved the customer’s concerns. After two months of shipping, a batch of high-quality duplex stainless steel pipes and fittings is about to arrive in the Middle East for the project.

https://www.xysteelpipe.com/five-delivery-schemes-to-win-middle-east-orders/

评论

此博客中的热门博文

The main reason for the porosity of submerged arc welding seam

Standard for Choosing Oil Casing Pipe Manufacturers

How to distinguish between ERW steel tube and seamless steel tube?